Daniel Lund III - LexologyAbsolutely not, said the Louisiana Fifth Circuit Court of Appeal to a masonry subcontractor being sued for allegedly improperly refusing to honor a subcontract bid.
A general contractor preparing its overall bid for a public project in Jefferson Parish relied in the process on the defendant masonry subcontractor’s bid. After a public bid process and receiving the award of the project, the general contractor was informed by the subcontractor that it believed that the unit price form that had been supplied to the sub “contained inaccuracies.” Notwithstanding offers by the GC to endeavor to address the purported “inaccuracies” during the project, most likely by a change order, the subcontractor refused to execute its subcontract. The general contractor then awarded the masonry work to another subcontractor for $368,222 more than the original sub’s bid.
The GC filed suit – for recovery of $368,222 – against the defendant subcontractor during the course of the public project. The defendant sub objected, arguing to the court that the lawsuit was “premature.” At the heart of the prematurity argument: the sub urging that the general contractor filed suit before its right to recover damages had accrued.
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Timely and Properly Assert Affirmative Defenses and Understand Statutory Conditions Precedent
August 05, 2024 —
David Adelstein - Florida Construction Legal UpdatesA recent case serves as a reminder to TIMELY and PROPERLY assert affirmative defenses and to understand statutory conditions precedent to construction lien claims. Failing to do one or the other could be severely detrimental to the position you want to take in a dispute, whether it is a lien foreclosure dispute, or any other dispute.
In Scherf v. Tom Krips Construction, Inc., 2024 WL 3297592 (Fla. 4th DCA 2024), the president of a construction company and his wife were building a residence. They orally accepted the proposal from the concrete shell contractor and asked for invoices to be submitted to the president’s construction company. No written contract was memorialized. The president and his wife did not pay the concrete shell contractor and the contractor recorded a lien and sued to foreclose on the lien. Years later (the case had been stayed because the president and his wife filed for bankruptcy and the shell contractor had to get leave of the automatic bankruptcy stay to pursue the lien foreclosure), the shell contractor moved for summary judgment. The president and his wife moved for leave to file an amended answer and affirmative defenses. They claimed the oral contract was with the construction company and the shell contractor was required to serve a Notice to Owner under
Florida Statute s. 713.06. Alternatively, they argued that if the oral contract was with the president and his wife, the shell contractor was required to serve a Final Contractor’s Payment Affidavit at least 5 days before filing its lien foreclosure claim, and did not, as required by s. 713.06.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
A New Study on Implementing Digital Visual Management
July 31, 2024 —
Aarni Heiskanen - AEC BusinessA new paper, “Implementing Digital Visual Management: A Case Study on Challenges and Barriers,” discusses situational management in complex infrastructure projects. It’s worth reading for anyone interested in improving project management with digital tools.
A complex infrastructure project
The authors interviewed nine project management professionals who worked for the client on constructing the western part of the Metro in Helsinki and Espoo, Finland. The project lasted eight years and had a budget of 1,200 million euros.
The project used a Digital Visual Management (DVM) tool, and the paper discusses the challenges and barriers faced during the tool’s implementation. At the time of the study, the system was used to manage the final documentation and testing status.
KPI management
The project management team was involved in developing a system for combining collected data into a central dashboard and using it to manage the whole project.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Los Angeles Wildfires Will Cause Significant Insured Losses, Ranking Amongst the Most Destructive in California's History
January 14, 2025 —
Morningstar DBRSWildfires currently burning in the Pacific Palisades, Eaton, Hurst and other Los Angeles neighborhoods will cause significant losses for the insurance industry, in
Morningstar DBRS’ view. The fires have already burned more than 1,100 homes and threaten more than 28,000 additional structures, according to local fire officials. Preliminary estimates point to total insured losses in excess of $8 billion depending on the final number of properties being affected by the wildfires. By way of comparison, the 2018 Woolsey Fire, which destroyed 1,643 structures just north of Los Angeles, caused more than $6 billion in property damages at that time. Morningstar DBRS expects the ongoing wildfires to have a negative but manageable impact on major property insurers active in the Californian market, with the impact somewhat mitigated by their use of reinsurance and their high degree of diversification. Similarly, losses should be manageable for the global reinsurance industry and not affect their credit profiles.
While leading U.S. property insurers are in good financial condition, the California property insurance market has been challenging because of high wildfire and other natural catastrophe risks combined with regulatory restrictions on coverage and pricing, leading many insurers to re-think their product offering, including an outright exit from the market. For example, market leaders such as State Farm and Allstate started reducing their exposure to the California market beginning 2022-2023. It is therefore possible that a larger than usual portion of the losses caused by the wildfires will be uninsured or may be covered under the California FAIR Plan, which is designed to provide fire coverage up to $3 million per home and spread the risk across the industry when it is not available from traditional carriers.
This event reinforces the need for adequate rate increases on home insurance in California, based on forward-looking pricing and catastrophe modelling, as well as for additional fire prevention and mitigation initiatives. However, property insurance affordability is likely to remain a challenge in the state going forward, with many property owners opting to remain uninsured or under-insured because of the high costs.
New Jersey Law Firm Announces $4 Million Settlement from Construction Site Accident
November 11, 2024 —
Greenberg Minasian, LLCWEST ORANGE, N.J., Nov. 07, 2024 (GLOBE NEWSWIRE) -- Greenberg Minasian, LLC, a personal injury law firm located in Essex County, New Jersey, has announced a $4 million settlement stemming from a roofer who suffered serious injuries after a construction site fall. Veteran trial attorney Mitchell Goldstein represented the injured client, who suffered multiple fractures and injuries, permanently affecting his ability to work.
In 2018, Robert Smith, who was 61 at the time, fell backward through or over a temporary guard rail at the American Dream Mall in East Rutherford, NJ. The 30-foot fall caused him to suffer serious injuries to his pubis, sacrum, clavicle, and humerus, leading to multiple surgeries and a hip replacement.
On behalf of his client, Mr. Goldstein brought suit against the mall developer and construction company, successfully arguing that the temporary guardrails were improperly constructed and insufficiently elevated according to Occupational Safety and Health Administration (OSHA) guidelines. The case was settled just two days before trial, marking a significant victory for the plaintiff and his family.
Despite the defense's attempt to argue that Mr. Smith was responsible for his fall, Goldstein was able to refute their claims, asserting that the temporary guardrail's improper construction directly led to the accident.
About Greenberg Minasian LLC
Based in West Orange, Greenberg Minasian represents clients who have been seriously injured as the result of negligence by others. The firm handles cases anywhere in New Jersey including West Orange, Jersey City, Newark, Essex County and all surrounding areas. The firm continues to achieve the highest awards for its clients and families.
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Surprising Dismissal of False Claims Act Case Based on Appointments Clause - What Does It Mean?
October 15, 2024 —
Steven H. Lee - Lewis Brisbois NewsroomAtlanta, Ga. (October 1, 2024) - In a surprising turn of events, the U.S. District Court for the Middle District of Florida recently dismissed a False Claims Act (FCA) lawsuit brought by relator Clarissa Zafirov against Florida Medical Associates, LLC, and other defendants. U.S. District Judge Kathryn Kimball Mizelle
ruled that the FCA’s qui tam provisions, which allow private individuals to bring lawsuits on behalf of the government, violate the Constitution’s Appointments Clause.
This decision follows another unexpected ruling by U.S. District Judge Aileen Cannon in the Southern District of Florida, where the court similarly dismissed an indictment against former President Donald Trump based on the same constitutional clause.
At the heart of these rulings is the argument that FCA relators - who decide whom to sue, which legal theories to pursue, and how to proceed - exercise significant executive authority. Because they are not appointed by the President, a department head, or a court, the judges concluded that these relators hold their positions unconstitutionally. As a result, Judge Mizelle dismissed the case entirely.
Read the full story...Reprinted courtesy of
Steven H. Lee, Lewis BrisboisMr. Lee may be contacted at
Steven.Lee@lewisbrisbois.com
There is No Presumptive Resumption!
January 21, 2025 —
Daniel Lund III - LexologyA Louisiana school board filed suit in court in 2018 on a construction project but was rebuffed based upon arguments by the general contractor and surety defendants. Those defendants asserted that the court filings were premature, based upon an arbitration clause in the general contract. The trial court agreed and stayed the litigation, “pending completion of arbitration.”
Arbitration was never filed. Interestingly, within the arbitration clause, the following language existed: “For statute of limitations purposes, receipt of written demand for arbitration shall constitute the institution of legal or equitable proceedings based upon the Claim.”
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com