Fall 2024 Legislative Update:
October 28, 2024 —
Joshua Lane - Ahlers Cressman & Sleight PLLCReview of (a) RCW 60.30.010-020, (b) RCW 49.17.530, (c) RCW 19.95.020, (d) RCW 39.116.005, et seq., (e) RCW 36.70B.080, and (f) RCW 39.12.010 and .13
While much of the focus on the recent legislative updates has been on RCW 39.04.360, a number of other legislative changes may also have significant impacts on Washington’s construction industry. Six of these changes are summarized below.
A. RCW 60.30.010 and .020 (SSB 6108) – Concerning Retainage on Private Construction, Effective June 6, 2024
Last year, ESSB 5528 imposed restrictions and obligations related to retainage and timing of final payment on private (non-public works) projects. It capped retainage at 5%, required prompt payment on final payments, and required owners to accept a retainage bond on private construction projects, excluding single-family residential construction less than 12 units.
This year, SSB 6108 adds suppliers to the statutes (RCW 60.30.010 and 0.020) pertaining to retainage on private construction projects.
Read the full story...Reprinted courtesy of
Joshua Lane, Ahlers Cressman & Sleight PLLCMr. Lane may be contacted at
joshua.lane@acslawyers.com
New York Construction Practice Team Obtains Summary Judgment and Dismissal of Labor Law Claims
October 01, 2024 —
Lewis Brisbois NewsroomNew York, N.Y. (August 23, 2024) – In Trujillo-Cruz v. City of New York, et al., New York Partner Inderjit Dhami, a member of New York Partner Meghan A. Cavalieri’s Construction Practice Team, recently obtained summary judgment and dismissal of the plaintiff's Labor Law §240(1), §241(6) and §200 claims dismissing the entire case against national developer and construction company clients.
The plaintiff alleged to have sustained injuries as the result of a construction site accident occurring on July 11, 2018, while in the scope of his employment as a laborer in connection with the construction/renovation of a residential apartment building in Brooklyn, New York. Specifically, the plaintiff alleged that he was injured when he was coming down from a ladder and fell on a 2”x 4”, causing him disabling injuries. The plaintiffs’ counsel articulated a $3 million settlement demand.
Labor Law §240(1) imposes absolute liability on a defendant where an injured worker engaged in the performance of covered construction work establishes that a safety device proved inadequate to shield him from elevation-related harm, and that the defendant’s failure to provide an adequate safety device proximately caused the injuries alleged. The plaintiff first testified that he stepped on the 2” x 4” after he came down off of the ladder, but his counsel then prompted him to recalibrate his testimony by asking whether the accident arose when he was coming down the ladder or after he had come down off of the ladder. The plaintiff changed his testimony, alleging that the accident arose as he was coming down the ladder and that he remained partially on the ladder when he stepped on the piece of formwork and fell. Inderjit argued that the plaintiff’s reframing of his deposition testimony was immaterial for purposes of the Labor Law § 240 (1) analysis. Irrespective of whether the plaintiff was on solid ground or had one foot on the ladder at the time of the occurrence, his Labor Law § 240 (1) claim was unavailing in that the accident did not arise as a result of the type of extraordinary elevation-related peril protected by Labor Law § 240 (1). Justice Maslow agreed and dismissed the plaintiff’s Labor Law § 240 (1) claims.
Read the full story...Reprinted courtesy of
Lewis Brisbois
Real Estate & Construction News Roundup (12/4/24) – Highest Rate of Office Conversions, Lending Caps for Fannie Mae and Freddie Mac and Affordability Challenges for Homebuyers
December 23, 2024 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, infrastructure-related ballot initiatives, U.S. Green Building Council’s success stories, support for sustainable building, and more!
- 2024 is expected to see the highest rate of office conversions since CBRE began tracking them in 2016. (Nish Amarnath, SmartCities Dive)
- The Federal Housing Finance Agency has established lending caps of $73 billion each for Fannie Mae and Freddie Mac, allowing them to purchase a total of up to $146 billion in multifamily loans in 2025. (Leslie Shaver, Multifamily Dive)
- A number of infrastructure-related initiatives with the potential to impact facilities managers were on the ballot during the 2024 U.S. presidential election. (Joe Burns, Construction Dive)
Read the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Supreme Court Opens Door for Challenges to Older Federal Regulations
August 05, 2024 —
Jane C. Luxton - Lewis BrisboisWashington, D.C. (July 1, 2024) – On July 1, 2024, the U.S. Supreme Court issued another end-of-term major decision limiting the scope of federal agency actions in Corner Post, Inc. v. Board of Governors of the Federal Reserve System. Adding to the tectonic shift in the regulatory landscape created by the Court’s June 27 and 28 rulings constraining the role of administrative law judges and overturning longstanding “Chevron deference” by courts to federal agency expertise, the decision in Corner Post establishes a newly expanded time frame for affected entities to challenge final agency action. Instead of confirming that final agency action is subject to a default six-year statute of limitations, the Court held that under the Administrative Procedure Act (APA), the time limit for appeal begins to run when a plaintiff is injured by the agency's action, not when the action becomes final. This decision has important implications for businesses and others affected by federal regulations.
The case arose when Corner Post, a truck stop and convenience store in North Dakota that opened in 2018, challenged a 2011 Federal Reserve Board regulation (Regulation II) that set maximum interchange fees for debit card transactions. Corner Post filed suit in 2021, arguing that Regulation II allowed higher fees than permitted by statute. The lower courts dismissed the suit as time-barred under 28 U.S.C. § 2401(a), which effectively requires APA claims to be filed "within six years after the right of action first accrues."
Read the full story...Reprinted courtesy of
Jane C. Luxton, Lewis BrisboisMs. Luxton may be contacted at
Jane.Luxton@lewisbrisbois.com
Sources of Insurance Recovery for Emerging PFAS Claims
December 17, 2024 —
Jasjeet K. Sahani - Saxe Doernberger & Vita, P.C.This year, the Environmental Protection Agency (“EPA”) issued its first-ever national, legally enforceable drinking water standard to protect communities from exposure to harmful per-and polyfluoroalkyl substances (“PFAS”), also known as “forever chemicals.”
[1] In addition, the Food and Drug Administration announced that grease-proofing materials containing PFAS are no longer being sold for use in food packaging in the United States.
[2] These are likely the first in a line of many PFAS regulations that will emerge as the harmful effects of PFAS are further understood. With this increasing regulatory focus on PFAS and their harmful effects, companies whose operations might involve these substances should be aware of what they are and potential sources of recovery for claims that arise from their omnipresence.
PFAS Background
According to the EPA, PFAS are widely used, long-lasting chemicals which break down slowly over time.
[3] PFAS can be found in thousands of items, including, but not limited to: pots and pans, cleaning products, fabric and leather coatings, firefighting foam, carpeting, roofing materials, paints, sealants, caulks, and adhesives.
[4] Additionally, manufacturing processes, waste storage, and treatment sites commonly release PFAS into the air, soil, and water.
[5] Read the full story...Reprinted courtesy of
Jasjeet K. Sahani, Saxe Doernberger & Vita, P.C.Ms. Sahani may be contacted at
JSahani@sdvlaw.com
In Matter of First Impression, California Appellate Court Finds a Claim for a Real Estate Professional’s Breach of Fiduciary Duty is Assignable
January 28, 2025 —
Briane Slome & Pamela Albanese - Lewis Brisbois NewsroomSan Diego, Calif. (January 17, 2025) - The California Court of Appeal recently reversed a judgment entered in favor of real estate brokers who were sued for breaching their fiduciary duties in connection with the sale of residential real estate in Malibu. The Court of Appeal found the trial court erred when it rendered judgment in favor of the brokers on the basis that the plaintiff lacked standing to pursue claims that had been assigned to her. The trial court reasoned that claims for breach of fiduciary duty against real estate brokers are highly personalized tort causes of action, which cannot be assigned. The Court of Appeal disagreed. In a case of first impression, it held that a cause of action for breach of a real estate broker’s fiduciary duties, which seeks damages related to property rights and pecuniary interests, is assignable.
The Court of Appeal’s decision in Lazar v. Bishop, issued December 19, 2024, involved a unique set of facts. The seller bought the property in 2006. His daughter, Laura Lazar, lived at the property. The seller hired a real estate broker to sell the home. The broker listed the property for $4.2 million. Thereafter, she persuaded the seller to drop the listing price to $3.15 million, the price at which it was ultimately sold.
Reprinted courtesy of
Briane Slome, Lewis Brisbois and
Pamela Albanese, Lewis Brisbois
Mr. Slome may be contacted at Brian.Slome@lewisbrisbois.com
Ms. Albanese may be contacted at Pamela.Albanese@lewisbrisbois.com
Read the full story...
Beyond the Flow-Down Clause: Subcontract Provisions That Can Expose General Contractors to Increased Liability and Inconsistent Outcomes
December 10, 2024 —
Phillip L. Parham III - ConsensusDocsFlow-down clauses in construction subcontracts—blanket clauses providing that some or all of the terms and conditions in the prime contract between the general contractor and the property owner apply equally between the subcontractor and general contractor—are an important component to managing risk for a general contractor and reducing the likelihood of disputes with either/both the owner and subcontractor. Put simply, flow-down provisions can provide continuity between the general contractor’s obligations to the owner and the subcontractor’s obligations to the general contractor. Properly drafted, flow-down clauses reduce the general contractor’s risk by ensuring that the subcontractor is legally bound to meet the owner’s objectives for the project in the same way as the general contractor. But relying on blanket flow-down clauses, alone, to protect the general contractor is like a soldier going into battle with nothing but a helmet, leaving significant other areas exposed and unprotected. In other words, a general contractor should look beyond just a singular, blanket flow down of terms to ensure its bases are properly covered.
Accordingly, this article goes beyond the blanket flow-down clause and highlights several key subcontract provisions where inconsistent obligations among the subcontractor, general contractor, and owner expose the general contractor to increased liability and inconsistent outcomes. Specifically, this article will examine disputes resolution clauses, liquidating provisions, notice provisions, and termination provisions. However, this article will not provide a deep examination of these clauses, nor does it highlight every potentially relevant clause. Rather, it focuses on these select clauses to highlight important issues associated with flow-down provisions.
Read the full story...Reprinted courtesy of
Phillip L. Parham III, Jones Walker LLPMr. Parham may be contacted at
pparham@joneswalker.com
Insured's Collapse Claim Survives Summary Judgment
October 28, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer's motion for summary judgment seeking to dispose of the insured's claim for collapse was denied. Life Skills, Inc. v. Harleysville Ins. Co., 2024 U.S. Dist. LEXIS 143658 (D. Mass. Aug. 13, 2024).
Life Skills was a non-profit social service agency providing residential and day habilitation services to adults with autism and intellectual and developmental disabilities. The head office was covered by a policy issued by Harleysville with building coverage limits of $3,038,300.
Damage occurred in a ceramics classroom located in the basement of the building. The floor sank between eight to twelve inches in the northeast corner. The ceramics classroom contained two large kilns weighing approximately 200 pounds.