Nine ACS Lawyers Recognized as Super Lawyers – Two Recognized as Rising Stars
August 26, 2024 —
Ahlers Cressman & Sleight PLLCGoing outside the norm of our blogs, which usually discuss construction related issues, Ahlers, Cressman, & Sleight is pleased to announce that nine members of our firm have been selected to the 2024 Washington Super Lawyers list.
Each year, a rigorous process that involves a nomination by peers and a third-party verification of honors, awards, verdicts, settlements, and other criteria relating to their work as an attorney, aims to select no more than five percent of the lawyers in Washington state from no more than seventy practice areas for this distinction. As mentioned, the first step in the process is to be evaluated on their work as an attorney, next candidates are evaluated by their peers and given ratings based on the information known about their work. Finally, candidates are grouped into four firm-size categories and final selections are made. The grouping process is done so that candidates are compared fairly to their peers by firm size, eliminating the potential unfairness that comes with comparing large and small firm outcomes and attorney practices.
The Rising Star list involves an even narrower criteria than the Super Lawyers list. The initial process is the same, however, candidates for the Rising Stars list must be under the age of forty or have less than ten years of experience. For this category less the two and a half percent of lawyers in Washington are selected, making this quite a feat for those who have accomplished the honor.
Read the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Developers Can Tap into DOE’s $400 Million for Remote and Rural Clean Energy Projects
December 10, 2024 —
Robert A. James, Elina Teplinsky, Alicia M. McKnight, Sidney L. Fowler & Clarence H. Tolliver - Gravel2Gavel BlogOn October 3, 2024, the Department of Energy Office of Clean Energy Demonstrations announced a Notice of Funding Opportunity (NOFO) to fund up to $400 million for clean energy projects in rural and remote areas via its Energy Improvements in Rural or Remote Areas program. The NOFO will provide awards ranging from $2 million – $50 million, with plans to fund 20 to 50 projects. Awards will require a non-federal cost share, range across four topic areas, and target projects in rural and remote communities with populations of 10,000 people or fewer.
Eligibility
Applications are open to a wide range of entities, including for-profit and nonprofit organizations, state and local governmental entities, Indian Tribes and Tribal organizations, institutions of higher education, rural electric cooperatives, incorporated and unincorporated consortia, farming associations and cooperatives, and labor unions. Generally applicants must be U.S. entities, but foreign entities may be allowed to participate in limited circumstances. Applicants must identify at least one area in the U.S. or U.S. territories with a population of up to 10,000 people which will benefit from the proposal.
Reprinted courtesy of
Robert A. James, Pillsbury,
Elina Teplinsky, Pillsbury,
Alicia M. McKnight, Pillsbury,
Sidney L. Fowler, Pillsbury and
Clarence H. Tolliver, Pillsbury
Mr. James may be contacted at rob.james@pillsburylaw.com
Ms. Teplinsky may be contacted at elina.teplinsky@pillsburylaw.com
Ms. McKnight may be contacted at alicia.mcknight@pillsburylaw.com
Mr. Fowler may be contacted at sidney.fowler@pillsburylaw.com
Mr. Tolliver may be contacted at clarence.tolliver@pillsburylaw.com
Read the full story...
Insurer's Motion for Summary Judgment to Dispose of Hail Damage Claim Fails
November 25, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment seeking to dismiss the insured's complaint requesting coverage for hail damage and a claim for bad faith. Rodriquez v. State Farm Lloyds, 2024 U.S. Dist. LEXIS 160007 (W.D. Tex. Sept. 5, 2024).
Mr. Rodriquez sought coverage under his homeowners policy after a hail and wind storm damaged his roof. After inspection, State Farm agreed that some minimal loss caused by hail was covered, but determined that the covered loss was less than the amount of the deductible. State Farm further determined that any hail damage to the roof was excluded by an endorsement, Exclusion of Cosmetic Loss to Metal Roof Coverings Caused by Hail. State Farm also determined that some damage was caused by previous faulty workmanship or wear and tear, both of which were excluded from coverage.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Robinson+Cole’s Amicus Brief Adopted and Cited by Massachusetts’s High Court
July 31, 2024 —
Erica Whaley - Construction Law ZoneEarlier this year, the
Associated Subcontractors of Massachusetts hired Robinson+Cole attorney
Joseph Barra to submit an amicus brief to the Massachusetts Supreme Judicial Court for consideration in the appeal pending before it in
Business Interiors Floor Covering Business Trust v. Graycor Construction Co., Inc. In its June 17, 2024 decision in that case, the Court interpreted the Massachusetts Prompt Pay Act, which applies to private construction projects and “requires that parties to a construction contract approve or reject payment within” an allotted time period and in compliance with certain procedures else such payments will be deemed approved. Two years ago, the Massachusetts Appeals Court, in
Tocci Building Corp. v. IRIV Partners, LLC, decided that an owner who fails to timely advise its general contractor of the reasons as to why it was withholding payment, coupled with failure to certify that such funds are being withheld in good faith, violates the Prompt Pay Act and makes the owner liable for funds owed.
[1] However, the Tocci Building Court left open the question of whether one who violates the Prompt Pay Act forfeits its substantive defenses to non-payment, such as fraud, defective work, or breach of material obligation of the contract.
The facts of Business Interiors involve a general contractor, Graycor, which subcontracted Business Interiors to perform certain flooring work for a movie theatre in Boston’s North End. When Graycor failed to formally approve, reject, or certify, in good faith, its withholding of payment of three of Business Interiors’ applications for payment as prescribed by the Prompt Pay Act, Business Interiors brought suit alleging, among other things, breach of contract. Business Interiors then moved for summary judgement arguing that Graycor’s failure to comply with the Act rendered it liable for the unpaid invoices.
Read the full story...Reprinted courtesy of
Robinson + Cole
Construction Defect Claim Survives Insurer's Summary Judgment Motion Due to Lack of Evidence
December 23, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment on a construction defect claim due to lack of evidence. Statesboro Erectors, Inc. v. Owners Ins. Co., 2024 U.S. Dist. LEXIS 176555 (N.D. Ga. Sept. 30, 2024).
Griffco was the general contractor for a construction project. King Steel was hired as the "steel fabricator." King Steel subcontracted with Statesboro Erectors to complete certain construction work at the site. Statesboro agreed to the complete, proper and safe erection of the structural steel.
A steel collapse occurred at the construction site. According to King Steel, the collapse "appeared to have occurred due to lack of temporary cables or bracing for steel columns." Because of the collapse, King Steel was required to supply additional materials to replace the structural damage caused by the collapse.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Designer of World’s Tallest Building Wants to Turn Skyscrapers Into Batteries
July 31, 2024 —
Will Wade - BloombergThe architecture firm that designed the world’s tallest building is considering ways to build skyscrapers that can store energy using gravity.
Skidmore, Owings & Merrill LLP has developed a series of prototype designs that use electric motors to elevate massive blocks, creating potential energy that can be converted into electricity when the blocks are lowered. The designs are based on technology developed by partner Energy Vault Holdings Inc. as an alternative to lithium-ion batteries and other types of chemical cells. They are seeking developer partners interested in offsetting greenhouse gas pollution from buildings, which the United Nations estimates are responsible for almost 40% of global emissions.
The concept is similar to widely used pumped hydroelectric plants. Energy Vault completed its first major project this month near Shanghai, a stand-alone storage system that can supply as much as 25 megawatts of power for four hours. Other companies are testing new types of gravity storage systems, including ones using abandoned oil wells and mines.
Read the full story...Reprinted courtesy of
Will Wade, Bloomberg
FEMA Fire Management Assistance Granted for the French Fire
July 08, 2024 —
The Federal Emergency Management AgencyOAKLAND, Calif. – The Federal Emergency Management Agency's (FEMA) Region 9 Administrator authorized the use of federal funds on July 4 at 11:37 p.m. PDT / 2:37 a.m. EDT to assist the state of California to combat the French Fire burning in Mariposa County.
On July 4, the state of California submitted a request for a Fire Management Assistance Grant (FMAG). At the time of the request, the fire threatened approximately 1,019 homes in and around Mariposa, CA, population 1,300. 95% of the threatened homes are primary residences and 5% are secondary residences.
The fire started on July 4, 2024 and had burned more than 790 acres of State and private land. The fire was 0% contained. There are five large fires burning uncontrolled within the State.
FMAGs provide federal funding for up to 75 percent of eligible firefighting costs. The Disaster Relief Fund provides allowances for FMAGs through FEMA to assist in fighting fires that threaten to become a greater incident.
Eligible costs covered by FMAGs can include expenses for field camps, equipment use, materials, supplies and mobilization, and demobilization activities attributed to fighting the fire.
For more information on FMAGs, visit https://www.fema.gov/assistance/public/fire-management-assistance.
A “Flood” of Uncertainty; Massachusetts SJC Finds Policy Term Ambiguous
August 26, 2024 —
Michael S. Levine & Torrye Zullo - Hunton Insurance Recovery BlogThe highest court in Massachusetts recently held that term “Flood” and the associated phrase “surface waters,” as used in two all-risk insurance policies, is ambiguous in the context of water that accumulated on a parapet roof and rooftop courtyard, thereby negating the insurers’ attempt to limit coverage to a sublimited coverage for “Flood.”
Background
In June 2020, a severe storm caused damage to Norwood Hospital, owned by Medical Properties Trust, Inc. (“MPT”) and leased to Steward Health Care System (“Steward”), the policyholders. The relevant portion of the damage included damage from rain that accumulated on the rooftop courtyard and seeped into the interior of the building causing damage to the building and its contents.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Torrye Zullo, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Zullo may be contacted at tzullo@HuntonAK.com
Read the full story...