Five Issues to Consider in Government Contracting (Or Any Contracting!)
September 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesThe appeal of Appeals of – Konecranes Nuclear Equipment & Services, LLC, ASBCA 62797, 2024 WL 2698011 (May 7, 2024) raises interesting, but important, issues that should be considered. In this case, the government (in a supply contract) procured four portal cranes from the claimant. After an initial test of one of the cranes failed, the government refused to accept delivery even after the issue was addressed by the claimant. The government did not accept the manner in which the claimant addressed the issue and would only accept cranes if the claimant employed “an unnecessary alternative solution [that] caused further delay and increased [claimant’s] costs.” On appeal, it was determined the government’s decision to delay delivery based on its demand for the alternative solution was not justified, i.e., constituted a breach of contract. Below are five issues of consideration in government contracting, or, for that matter, any contracting.
Issue #1- Patently Ambiguous Specifications
The government argued that the specifications were patently ambiguous and because the claimant failed to inquire regarding the ambiguous specifications prior to performance, its interpretation of the ambiguous specifications should govern. The contractor countered that the specifications were unambiguous and it met the specifications.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
GSA Releases Updated Standards to Accelerate Federal Buildings Toward Zero Emissions
August 12, 2024 —
The U.S. General Services AdministrationWASHINGTON — The U.S. General Services Administration (GSA) is advancing progress toward the Biden-Harris Administration's federal sustainability goals by releasing updated standards for federal buildings. P100 Facilities Standards for the Public Buildings Service establish mandatory design and construction standards and performance criteria for 300,000 federal buildings nationwide. The updated standards will help advance the adoption of cleaner, more efficient technologies for buildings; lead the way towards realizing the goals of the Federal Sustainability Plan to achieve net-zero emissions from all federal buildings by 2045; and promote the use of American-made, low carbon construction materials.
P100 requires that facilities adopt advanced energy conservation strategies and eliminate on-site fossil fuel use, directives that align with federal sustainability goals and will accelerate the transition to a clean energy economy. The industry-leading standard calls for grid-interactive efficient buildings, leverages innovative technologies through GSA's Green Proving Ground, requires the use of low-embodied carbon materials, and directs potable water reuse. These comprehensive measures ensure that new and renovated federal facilities achieve peak performance while minimizing environmental impact.
The 2024 P100 establishes exceptional benchmarks for:
- Electrification: New standards for building equipment and systems to be powered by clean energy sources.
- Embodied Carbon: Requirement to utilize low-embodied carbon materials, including salvaged, reused, regenerative, and biomimetic options.
- Energy Efficiency: Enhanced building envelope performance to minimize energy loss and improve overall efficiency.
- Grid-Interactive Efficient Buildings: New measures to support a more resilient, responsive grid.
- Water Reuse: Mandating that buildings have a 15% potable water reuse rate.
- Construction Decarbonization: Ground breaking new low-carbon methods for constructing federal buildings including clean energy operations, material salvage, and offsite assemblage.
- Labor Practices: New standards protecting workers from unfair or unsafe labor practices, ensuring supply chains are free from child and forced labor and that workers are protected from the impacts of extreme heat.
P100 is updated and published every three years. For more detailed information on the 2024 P100 and other GSA initiatives, visit www.gsa.gov/p100.
Rainwater Collecting on Rooftop is not Subject to Policy's Flood Sublimits
October 15, 2024 —
Tred R. Eyerly - Insurance Law HawaiiResponding to a certified question from the First Circuit, the Supreme Judicial Court of Massachusetts determined that rainwater collecting on the insureds' rooftop and causing interior damage was not "flood" as defined in the policy and subject to sublimits. Zurich Am. Ins. Co. v. Medical Properties Trust, Inc., 2024 Mass. LEXIS ___ (Mass. July 23, 2024).
A severe thunderstorm caused heavy rain and strong winds which damaged a hospital. The hospital was owned by Medical Properties Trust, Inc. (MPT) and leased to Steward Health Care System LLC (Steward). Ground water accumulated and flooded the basement. Rainwater also accumulated on the hospital's parapet roofs and on the second-story courtyard, and eventually seeped through the parapet roofs and courtyard to the hospital's upper floors, causing damage to the building and property within.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
In Appellate Division First, New York Appellate Team Successfully Invokes “Party Finality” Doctrine to Obtain Dismissal of Appeal for Commercial Guarantors
December 23, 2024 —
Dean Pillarella - Lewis BrisboisNew York, N.Y. (November 20, 2024) - In Roc-Le Triomphe Associates, LLC v. DeSouza, 2024 NY Slip Op 05654 (1st Dep’t 2024), Associate Dean Pillarella, a member of the Appellate Practice, successfully invoked the party finality doctrine to obtain the dismissal of an appeal for the firm’s commercial guarantor clients.
The action concerned rent allegedly due and owing under a commercial lease by the lease’s tenant and guarantors. Pursuant to a 2022 order, the guarantors were awarded summary judgment and dismissal of all claims against them, with the landlord’s claims against the tenant left intact. After the decision and order was served with notice of entry by the prevailing party, the landlord did not file a notice of appeal from the order but, instead, filed a notice of appeal from a later judgment months after the time to appeal the order had expired.
Read the full story...Reprinted courtesy of
Dean Pillarella, Lewis BrisboisMr. Pillarella may be contacted at
Dean.Pillarella@lewisbrisbois.com
Insured's Claim for Water Damage Dismissed with Leave to Amend
August 12, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss the insured's claim for water damage under a homeowners' policy, but granted leave to amend. Thompson v. State Farm Gen. Ins. Co., 2024 U.S. Dist. LEXIS 98486 (C.D. Cal. June 3, 2024).
The insureds' first amended complaint alleged they "suffered a sudden and accidental water loss below their slab in their home." A plumber hired by the insureds discovered "a copper pipe burst inside a structural concrete footing between a manifold in the living room and the water heater." The insureds notified their insurer, State Farm.
Claim adjuster Andrea Acevedo conducted a visual inspection. The complaint alleged she did not "inspect or view the pipe, or have a testing conducted on the pipe." Acevedo sent a letter denying the insureds' claim based upon her finding that "because the loss was caused by a slab leak, there is no coverage available for the loss." The letter explained that the hot water supply line under the home failed due to wear, tear, deterioration and/or electrolysis. The predominant cause of loss to the failed pipe was due to one or a combination of rust, electrolysis, corrosion, wear, tear and/or deterioration. The policy did not cover water damage caused by water from below the surface of the ground. Further coverage for wear, tear, deterioration, rot, mold, maintenance, water from below the surface of the ground and a continuous or repeated seepage or leakage of water was excluded.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Litigation Roundup: “You Can’t Make Me Pay!”
August 19, 2024 —
Daniel Lund III - LexologyThe foregoing is an accurate statement, generally speaking, for Louisiana public entities. Statutory and constitutional provisions in Louisiana protect public entities from being forced to pay monies – including satisfying court judgments – when the monies have not been specifically allocated for the purpose. Correspondingly, there is ordinarily no means to seize public assets to satisfy judgments.
On the other hand, writs of mandamus in Louisiana – actions designed to compel a public official to undertake a ministerial duty over which the public official has no discretion – can be aimed at forcing a public official (on behalf of the public entity) to pay money.
In an inverse condemnation case, plaintiffs prevailed on the theory that a Louisiana public entity had “damaged and interfered with their use and enjoyment of their private homes and church” during a New Orleans drainage project. The plaintiffs pursued a writ of mandamus to compel payment their approximately $1.5 million judgment for damages and fees as a “ministerial duty” of the public entity. To be sure, in connection with the judgment, the public entity had not at any time specifically allocated funds for the payment.
Read the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
68 Lewis Brisbois Attorneys Recognized in 5th Edition of Best Lawyers: Ones to Watch in America
September 23, 2024 —
Lewis Brisbois Newsroom(August 15, 2024) – 68 Lewis Brisbois attorneys across 26 offices have been named to the 5th edition of “Best Lawyers: Ones to Watch in America.” Congratulations to the following attorneys on this recognition!
You can see the list of Lewis Brisbois attorneys named to Best Lawyers' 30th edition of The Best Lawyers in America here.
Reprinted courtesy of
Lewis Brisbois
Read the full story...
Repairs to Water Infrastructure Underway After Hurricane Helene
October 07, 2024 —
Derek Lacey - Engineering News-RecordAs transportation officials in Tennessee and North Carolina brace for long rebuilds of heavily damaged interstates in remote and rugged areas of the Appalachian Mountains, local agencies are also at work restoring water and sewer services to residents nearly one week after Hurricane Helene made landfall.
Reprinted courtesy of
Derek Lacey, Engineering News-Record
Mr. Lacey may be contacted at laceyd@enr.com
Read the full story...