Finding Insurer's Declaratory Relief Action Raises Unsettled Questions of State Law, Case is Dismissed
November 05, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe federal district court for the District of Hawaii dismissed the insurer's action for declaratory relief because it raised issues that were unsettled by Hawaii courts. Association of Apartment Owners of Lahaina Residential Condominium, et al., No. 1-24-cv-00075-JAO-BMK, Order Granting AOAO's Motion to Dismiss (D. Haw. Aug. 29, 2024).
The case addressed whether a property damage exclusion barred coverage over an owner's claim that a condominium association and its property manager failed to obtain adequate insurance before the condominium's property was damaged by the Maui wildfire in August 2023. Great American filed suit seeking a declaration that it had no duty to defend or indemnify the Association and the property manage, Quam Properties Hawaiiana, Inc., in connection with a demand for mediation submitted to the Association and Quam on behalf of one of the owners.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurer's Motion for Summary Judgment to Dispose of Hail Damage Claim Fails
November 25, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insurer's motion for summary judgment seeking to dismiss the insured's complaint requesting coverage for hail damage and a claim for bad faith. Rodriquez v. State Farm Lloyds, 2024 U.S. Dist. LEXIS 160007 (W.D. Tex. Sept. 5, 2024).
Mr. Rodriquez sought coverage under his homeowners policy after a hail and wind storm damaged his roof. After inspection, State Farm agreed that some minimal loss caused by hail was covered, but determined that the covered loss was less than the amount of the deductible. State Farm further determined that any hail damage to the roof was excluded by an endorsement, Exclusion of Cosmetic Loss to Metal Roof Coverings Caused by Hail. State Farm also determined that some damage was caused by previous faulty workmanship or wear and tear, both of which were excluded from coverage.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Federal Court Holds that Demolition Exclusion Does Not Apply and Carrier Has Duty to Defend Additional Insureds
September 02, 2024 —
Craig Rokuson - Traub LiebermanIn the recent case of
Travelers Indem. Co. v. Trisura Specialty Ins. Co., 2024 U.S. Dist. LEXIS 101953 (S.D.N.Y. June 7, 2024), the court had occasion to consider the classic additional insured fact pattern of a construction accident. Travelers insured the general contractor and provided a defense to the general contractor as well as its wholly owned subsidiary. Trisura insured the subcontractor, who employed the injured worker. Travelers brought suit, alleging that Trisura is obligated to defend and indemnify the general contractor, its subsidiary, the owner of the building (The City of New York), and the tenant.
Trisura denied any obligation to provide coverage due to the application of the “Demolition Exclusion” to the Trisura policy, which provides, in part, that there is no coverage for injury or damage arising out of the demolition of any building or structure which has original ground height in excess of three stories. The accident occurred during the interior demolition of the fifth floor of the building. The court held that the Demolition Exclusion applies only when there is a complete tearing down, razing, or destruction of an entire building. As the accident occurred during interior demolition, the exclusion did not apply.
Read the full story...Reprinted courtesy of
Craig Rokuson, Traub LiebermanMr. Rokuson may be contacted at
crokuson@tlsslaw.com
Updates to AIA Contract Applications
January 07, 2025 —
Anand Gupta - Construction Law Zone BlogThe construction industry often relies on contract forms drafted by the American Institute of Architects (AIA). These AIA forms include agreements between owners, designers, consultants, contractors, subcontractors, and construction managers. Some prefer to use the forms in the stock form, but others prefer to modify the language to their benefit. These modifications can be made in Microsoft Word and uploaded into AIA’s current web-based system, ACD5, to create redlines against the standard AIA forms (Checked-Drafts) and final clean versions without the “DRAFT” watermarks. Law firms and clients keep repositories of these modified templates for future projects.
A common issue with modifying documents offline in Microsoft Word and passing the documents back-and-forth between different email and document management systems is that the metadata of the forms becomes corrupted. AIA technical support then must reset the metadata, which takes hours or days. This delay can pose challenges to clients when they are up against a deadline.
Read the full story...Reprinted courtesy of
Anand Gupta, Robinson+ColeMr. Gupta may be contacted at
agupta@rc.com
Understanding Entitlement to Delays and Proper Support
December 10, 2024 —
Andrew G. Vicknair - The Dispute ResolverIn a previous
post, we discussed delays on construction projects including (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. We also reviewed the common methods of delay analysis include (1) the Total Cost Method, (2) the Modified Total Cost Approach, and (3) the Measured Mile Method.
Once you have determined the type of delay and the method to be used to analyze and quantify the delay, it is important to understand the type of documents/evidence needed to support your claim for delay.
If a party determines that they are entitled to some type of recovery for the delay, the party making a claim for delay, such as a contractor, must have the proper documentation/evidence to assist in proving entitlement for damages from the delay. Without the proper back-up, contractors are generally unable to recover all of the additional costs and expenses associated with the delays or, at best, recover only an “equitable” amount. Generally, damages must be proved with reasonable certainty and may not be based on speculation or conjecture. Thus, it is crucial for a party asserting a delay to have the proper documentation to support a delay claim, if the goal is to recover the damages associated with the delay.
Read the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
In Phoenix, Crews Thread Needle With $730M Broadway Curve Revamp
July 31, 2024 —
Scott Blair - Engineering News-RecordMotorists scrambling to dart across three lanes of traffic when merging onto the freeway. Vehicles slowing to a crawl due to extremely curved exit ramps. Commuters enduring agonizing backups as three freeways converge in a tight footprint. Bicyclists and pedestrians sweating through long detours to traverse freeways.
Reprinted courtesy of
Scott Blair, Engineering News-Record
Mr. Blair may be contacted at blairs@enr.com
Read the full story...
The Final Frontier Opens Up New Business Opportunities for Private Contractors
August 26, 2024 —
Jessica S. Allain - ConsensusDocsEarlier this year, the U.S. Department of Defense (“DOD”) issued its Commercial Space Integration Strategy. While arguably still in the early stages of implementation, this policy shows a significant shift in creating new opportunities for contractors to work with and sell commercial solutions to DOD. This creates big opportunities for the construction industry. DOD’s current construction budget is over $2.9 billion,[1] and seeking to increase funding and projects with the private sector also increases the need for construction of facilities to house those partnerships. For contractors who may be able to take advantage of these opportunities and the facilities that support them, it is worth having an understanding of what a prospective contractor would need to do to participate and what pitfalls may be attached to these programs.
In an effort to call out the elephant in the room, the timing of these policies coming out in the year before an election should not be ignored. While grounded in the 2022 National Defense Strategy and other established departmental policies, a change in administration could create change in how these prospective opportunities are handled.
Read the full story...Reprinted courtesy of
Jessica S. Allain, Jones WalkerMs. Allain may be contacted at
jallain@joneswalker.com
Consider Arbitration Provision in Homebuilder’s Warranty and Purchase-and-Sale Agreement
November 18, 2024 —
David Adelstein - Florida Construction Legal UpdatesWhen you enter into a contract with a homebuilder, particularly a tract homebuilder, please consider two things when it comes to dispute resolution: (1) your purchase-and-sale agreement likely contains an arbitration provision, and (2) your limited warranty agreement you get in connection with closing likely also reinforces the arbitration provision, especially with warranty claims governed by the limited warranty agreement. This dispute resolution is important because it means the homebuilder wants disputes resolved through the arbitration process and NOT through the litigation process (where the nature of disputes and allegations are public).
Look, there are pros and cons with arbitration, no different than litigation. Arbitrating a dispute is not necessarily a bad thing, and with certain disputes, ideal. There is no right to appeal in arbitration, but the dispute should resolve itself quicker than litigation, and you’ll have more control over the decision maker, i.e., the arbitrator.
Read the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com