COVID-19 Business Interruption Claims Four Years Later: What Have We Learned?
September 23, 2024 —
Patrick McKnight - The Dispute ResolverFour and half years ago the COVID-19 pandemic spread around the globe, bringing with it interesting, but challenging, legal problems for construction attorneys. Construction projects ground to a halt. Ever-changing guidance from authorities ranging from the U.S. Department of Labor to local health authorities resulted in a web of evolving obligations for general contractors and subs alike. One of the most closely watched legal questions was the wave of business interruption claims filed by plaintiffs, many of whom owned businesses impacted by government shutdowns. During the opening months of the pandemic, I
noted that hundreds of business interruption claims had been filed by insureds across the country. At that time, the only thing certain was that although the outcome remained unknown, virus exclusions were likely to become more likely in the future. Needless to say, much has happened since early 2020.
What does the data say about the outcome of business interruption claims?
In sum, plaintiffs have had an uphill battle. A helpful resource for analyzing the outcome of business interruption suits is the
Covid Coverage Litigation Tracker (“Tracker”), an insurance law analytics tool offered by Penn Carey Law of the University of Pennsylvania. According to its website, “[t]he Covid Coverage Litigation Tracker is a multi-sourced database and dashboard through which to view the unfolding insurance litigation arising out of the pandemic in federal and state courts. Widely cited in briefs, judicial opinions, and the press, the tracker also serves as a proof of concept for new methods to identify, track, and understand emerging case congregations in real time.”
Read the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
New York's New Gateway: The Overhaul of John F. Kennedy International Airport
September 09, 2024 —
Aileen Cho - Engineering News-RecordOn the cusp of the 70th anniversary of the originally named New York Airport’s opening in Queens, N.Y., a blue-ribbon panel in 2017 released a report to the governor of New York: The facility, once popularly known as Idlewild Airport, needed a comprehensive master plan and a total transformation. In the seven years since, builders at John F. Kennedy International Airport have been anything but idle, and the speed at which that $19-billion transformation of the roads and terminals is occurring could be called wild.
Reprinted courtesy of
Aileen Cho, Engineering News-Record
Ms. Cho may be contacted at choa@enr.com
Read the full story...
New ConsensusDocs 242 Design Professional Change Order Form Helps Facilitate Compensation for Changes in Design Services
November 05, 2024 —
Brian Perlberg - ConsensusDocsConsensusDocs is publishing a new ConsensusDocs 242 Change in Services and Compensation, a change order for design services by a design professional. In the design and construction industry, one thing is certain – change. The work scope included in basic design services an architect or engineer provides occurs somewhat regularly. Previously, ConsensusDocs did not have a standard contract document for changing design professionals’ prices. As a result of user feedback, the ConsensusDocs Contract Content Advisory Council (CCAC) drafted this new architect/engineer change order. The CCAC unanimously approved the new contract document and publication is set for October 14, 2024. The document will be available for most ConsensusDocs subscribers. The full, owner, design-professional, and short-form subscription packages will include the document. A subscription package can be purchased through ConsensusDocs here.
The design professional change order helps owners of construction projects keep track of additional services their design professionals perform. The design professional must provide itemized labor breakdowns for each invoice. The new ConsensusDocs 242 has options for compensation to be actual hours at the billing rate or a lump sum. The new contract document form also has a table for the remaining project deliverables and their respective due dates.
Read the full story...Reprinted courtesy of
Brian Perlberg, ConsensusDocs CoalitionMr. Perlberg may be contacted at
bperlberg@ConsensusDocs.org
A New Study on Implementing Digital Visual Management
July 31, 2024 —
Aarni Heiskanen - AEC BusinessA new paper, “Implementing Digital Visual Management: A Case Study on Challenges and Barriers,” discusses situational management in complex infrastructure projects. It’s worth reading for anyone interested in improving project management with digital tools.
A complex infrastructure project
The authors interviewed nine project management professionals who worked for the client on constructing the western part of the Metro in Helsinki and Espoo, Finland. The project lasted eight years and had a budget of 1,200 million euros.
The project used a Digital Visual Management (DVM) tool, and the paper discusses the challenges and barriers faced during the tool’s implementation. At the time of the study, the system was used to manage the final documentation and testing status.
KPI management
The project management team was involved in developing a system for combining collected data into a central dashboard and using it to manage the whole project.
Read the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Rhode Island Sues 13 Industry Firms Over Flawed Interstate Bridge
September 23, 2024 —
Richard Korman - Engineering News-RecordIn an attempt to recoup any money Rhode Island will owe to others for rerouting traffic on half of a high-volume interstate bridge in Providence after structural flaws had been detected, the state Dept. of Transportation filed a lawsuit Aug. 16 against 13 engineers and contractors that had inspected or performed work on the Washington Bridge in the last decade.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story...
Understanding Insurance Disputes in Construction Defect Litigation: A Review of Acuity v. Kinsale
December 17, 2024 —
David M. McLain – Colorado Construction Litigation BlogConstruction projects are inherently complex, and insurance coverage plays a crucial role in managing risks, especially when unforeseen issues arise. The case of Acuity v. Kinsale demonstrates the tangled web of insurance obligations, especially when multiple insurers provide coverage for a single event. This case, involving Monarch Stucco, Inc., Acuity, and Kinsale Insurance Company, sheds light on the challenges that contractors, subcontractors, and insurers may face when disputes over liability and coverage occur.
The Background of the Case
At the heart of this dispute lies a construction defect at a retirement community project in Lakewood, Colorado. Monarch Stucco, Inc. (“Monarch”), a subcontractor hired by GH Phipps Construction Company (“Phipps”), was responsible for stucco work on the project. Unfortunately, defects in the building’s envelope system, particularly Monarch’s stucco work, led to significant damage and costly repairs.
Read the full story...Reprinted courtesy of
David M. McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Parks and Degradation: The Mess at Yosemite
September 09, 2024 —
Laura Bliss - BloombergA couple of miles past the western entrance to Yosemite National Park, visitors pass from California into a postcard. The road opens to a majestic view of
Half Dome, El Capitan and Cathedral Rocks—celebrity peaks if ever there were—which form the towering walls of Yosemite Valley. On the pine-scented floor of John Muir’s mountain mansion, the Merced River flows gently by the side of the road as signs point toward trailheads and tourist destinations. Not far from
Curry Village, a cluster of tent cabins and eateries at the eastern end of the road, is a section of employee housing known as the Stables. It was there that Erin Rau found herself wrapped in a sleeping bag one broiling afternoon last summer, wondering whether she was about to die.
Rau was a little over a month into a seasonal job selling goods in the village’s general store. Almost as soon as she arrived from Michigan, she recalls, she got the sense this wouldn’t be the carefree, post-college summer gig she’d imagined. In the evenings, she was left alone to manage a bunch of fellow early-twentysomethings making the same sixteenish bucks an hour until the shop closed at 10. At night a family of ringtail possums would crawl down from the rafters to tear into a display of baked goods, a long-standing issue she says her bosses did nothing to resolve, apart from throwing away half-eaten muffins in the morning. Similarly, deer mice kept leaving droppings on the pillows and sheets in the cabin Rau shared with three other women. When one of her roommates complained, she says, management supplied a Ziploc with a couple of mouse traps, a mask, gloves and some hand wipes, leaving the employees to sort out the rest.
Read the full story...Reprinted courtesy of
Laura Bliss, Bloomberg
Delays and Suspension of the Work Under Fixed Price Government Contract
July 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v General Services Administration, 2024 WL 1953697, CBCA 7759 (CBCA 2024), a contractor entered into a fixed price contract with the government to repair, replace, and modernize site and building systems at a federal building. The contractor commenced work right before Covid-19. When Covid-19 hit, the government issued the contractor a two-week suspension of work notice on March 27, 2020. The suspension of work allowed off-site administrative work to continue but suspended on-sit
Bill Proposes First-Ever Federal Workforce Housing Tax Credit for Middle-Class HousingThe 2019 ISO Forms: Additions, Revisions, and PitfallsDenial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari ReliefUCP Buys Citizen HomesTexas Allows Wide Scope for Certificate of MeritBuilding Down in November, Even While Home Sales RiseCourt Adopts Magistrate's Recommendation t
Signed, Sealed and (Almost) Delivered: EU Council Authorizes Signing of U.S. – EU Bilateral Insurance Agreement
Insurer's Motion to Dismiss "Redundant Claims" Denied
No Interlocutory Appeals of "Garden-Variety" Contract Disputes
Lewis Brisbois Ranks Among Top 25 Firms on NLJ’s 2021 Women in Law Scorecard
Corvette museum likely to keep part of sinkhole
Florida High-Rise for Sale, Construction Defects Possibly Included
Factual Issues Prevent Summary Judgment Determination on Coverage for Additional Insured
Beyond Inverse Condemnation in Wildfire Litigation: An Oregon Jury Finds Utility Liable for Negligence, Trespass and Nuisance
Return-to-Workplace Checklist: Considerations and Emerging Best Practices for Employers
New Jersey Construction Company Owner and Employees Arrested for Fraud
Mediating Contract Claims and Disputes at the ASBCA
Famed NYC Bridge’s Armor Is Focus of Suit Against French Company
Genuine Dispute Summary Judgment Reversed for Abuse of Discretion and Trial of Fact Questions About Expert Opinions
Electronic Signatures On Contracts: Are They Truly Compliant?
Beam Fracture on Closed Mississippi River Bridge Is at Least Two Years Old
Fungi, Wet Rot, Dry Rot and "Virus": One of These Things is Not Like the Other
Nation’s Top Court Limits EPA's Authority in Clean Air Case
Code Changes Pave Way for CLT in Tall Buildings and Spark Flammability Debate
Additional Insured Not Entitled to Coverage for Named Insured's Defective Work
Construction Defects #10 On DBJ’s Top News Stories of 2015
AB 3018: Amendments to the Skilled and Trained Workforce Requirements on California Public Projects
Issues of Fact Prevent Insurer's Summary Judgment Motion in Collapse Case
HOA Has No Claim to Extend Statute of Limitations in Construction Defect Case
Dorian Lashes East Canada, Then Weakens Heading Out to Sea
Hurdles with Triggering a Subcontractor Performance Bond
'Major' Mass. Gas Leak Follows Feds Call For Regulation Changes One Year After Deadly Gas Explosions
Traub Lieberman Attorneys Lisa M. Rolle and Justyn Verzillo Win Motion for Summary Judgment
Eight Things You Need to Know About the AAA’s New Construction Arbitration Rules
Home Prices in U.S. Rose 0.3% in August From July, FHFA Says
Seven Coats Rose Attorneys Named to Texas Rising Stars List
America’s Bridges and the Need for Bridge Infrastructure Investment
Insurance Policy to Protect Hawaii's Coral Reefs
Haight has been named a Metropolitan Los Angeles Tier 1 “Best Law Firm” in four practice areas and Tier 2 in one practice area by U.S. News – Best Lawyers® “Best Law Firms” in 2021
City Sues over Leaking Sewer System
Conflicts of Laws, Deficiency Actions, and Statutes of Limitations – Oh My!
Where Breach of Contract and Tortious Interference Collide
Tender the Defense of a Lawsuit to your Liability Carrier
NYC Airports Get $500,000 Makeover Contest From Cuomo
Court of Appeal Puts the “Equity” in Equitable Subrogation
U.S. Army Corps Announces Regulatory Program “Modernization” Plan
Payment Bond Surety Entitled to Award of Attorneys’ Fees Although Defended by Principal
Traub Lieberman Partner Colleen Hastie Wins Summary Judgment in Favor of Sub-Contracted Electrical Company
Orlando Commercial Construction Permits Double in Value
The 411 on the New 415 Location of the Golden State Warriors
Traub Lieberman Partner Eric D. Suben and Associate Laura Puhala Win Summary Judgment in Favor of Insurer, Determining it has No Duty to Defend
Procedural Matters Matter!
Flint Water Crisis and America’s Clean Water Access Failings
Corps Spells Out Billions in Infrastructure Act Allocations
California Reinstates COVID-19 Supplemental Paid Sick Leave
Failure to Timely File Suit in Federal Court for Flood Loss is Fatal