New York Revises Retainage Requirements for Private Construction Contracts: Overview of the “5% Retainage Law”
January 22, 2024 —
Levi W. Barrett, Patrick T. Murray, Skyler L. Santomartino & Mark A. Snyder - Peckar & Abramson, P.C.On November 17, 2023, the State of New York enacted the “5% Retainage Law.” This legislation effectively limits the amount of retainage that can be held from general contractors and subcontractors to no more than 5%. It applies to many but not all construction contracts. In addition, the new law revises late stage billing requirements, enabling contractors to invoice for retainage at substantial completion. Previously, the parties to a construction contract were free to negotiate any retainage amount, limited only by an unspecified “reasonable amount” that would be released as the parties contractually set forth.
Summary
The new law amends Sections 756-a and 756-c of the General Business Law (part of Article 35E of the GBL, known as the “Prompt Pay Act”), and applies to private construction contracts “where the aggregate cost of the construction project, including all labor, services, materials and equipment to be furnished, equals or exceeds one hundred fifty thousand dollars.”
Reprinted courtesy of
Levi W. Barrett, Peckar & Abramson, P.C.,
Patrick T. Murray, Peckar & Abramson, P.C.,
Skyler L. Santomartino, Peckar & Abramson, P.C. and
Mark A. Snyder, Peckar & Abramson, P.C.
Mr. Barrett may be contacted at lbarrett@pecklaw.com
Mr. Murray may be contacted at pmurray@pecklaw.com
Mr. Santomartino may be contacted at ssantomartino@pecklaw.com
Mr. Snyder may be contacted at msnyder@pecklaw.com
Read the full story...
Just How Climate-Friendly Are Timber Buildings? It’s Complicated
February 12, 2024 —
Eric Roston - BloombergThis article is part of the Bloomberg Green series Timber Town, which looks at the global rise of timber as a low-carbon building material.
The number of people living in urban areas around the world
will swell by upwards of 2 billion over the next three decades. Many of those people will need new homes. But building those with conventional materials would unleash a gusher of carbon dioxide: Concrete, steel, glass and bricks for construction make up a combined
9% of global CO2 emissions, according to research by the United Nations Environment Program.
Enter engineered wood, a seemingly no-brainer solution.
Mass timber is not the typical lumber that has structured single-family houses in North America for decades. The wood components are strong enough to hold up an office tower or apartment block, and building with them is thought to emit much less CO2 than using standard materials. And since wood is about 50% carbon, the material itself even stores a little carbon, to boot.
Read the full story...Reprinted courtesy of
Eric Roston, Bloomberg
AGC’s 2024 Construction Outlook. Infrastructure is Bright but Office-Geddon is Not
February 12, 2024 —
Garret Murai - California Construction Law BlogThe Associated General Contractors of America has issued its
2024 Construction Outlook. According to its survey of construction contractors throughout the United States, contractors have a mixed outlook for 2024 with firms predicting transitions in the demand for projects, the types of challenges they will face and technologies they plan on embracing. According to the survey, contractors continue to cope with significant labor shortages, the impact of higher interest rates and input costs and a supply chain which, while better than in past few years, is still far from normal.
Of the 17 categories of construction types included in the survey, respondents expected a net positive growth in 14 of those categories, with infrastructure projects leading the net positive readings following the passage of the
Infrastructure Bill in 2021, and commercial retail and office leading the net negative readings as a result of the continuing
office-geddon:
Read the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Unpredictable Power Surges Threaten US Grid — And Your Home
April 08, 2024 —
Naureen S Malik - BloombergPaul LeBlanc was barefoot when he stepped outside that morning.
He was taking the trash out when he saw the red glow of flames engulfing a nearby home. A former firefighter, LeBlanc grabbed his shoes before racing across the street. He smashed a window, then rushed inside. The only person believed to be home was a teenage boy who had already escaped, luckily with just minor burns. Alarms blared “fire” loudly, again and again, blasting from homes through the area.
“I’ve been in buildings without protection before — I just wanted to make sure no one was stuck in there,” said LeBlanc, who spent more than three decades as a firefighter before retiring.
The damage to the Alonge family’s four-bedroom home built in the early 1800s was so bad they haven’t been able to return since the blaze in June. The source of the conflagration in Waltham, Massachusetts, came from a facility about 2 miles west of the home. An electric substation, which had been dealing with a rodent infestation, had a sudden, unstable surge in voltage.
Read the full story...Reprinted courtesy of
Naureen S Malik, Bloomberg
Congratulations to BWB&O’s Newport Beach Team for Prevailing on a Highly Contested Motion to Quash!
January 08, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPCongratulations to Newport Partners Tyler Offenhauser and Jonathan Cothran, and Associate Anisha Kohli, who recently prevailed on behalf of BWB&O’s client before the Orange County Superior Court on a highly contested Motion to Quash Service based on Plaintiff’s failure to timely file and serve a DOE Amendment, naming our client.
BWB&O’s client was the owner of a building where Plaintiff, a licensed electrician, was electrocuted while performing an upgrade to the building’s electrical infrastructure. Plaintiff’s original lawsuit named only the building’s tenant, who was also represented by BWB&O. BWB&O was successful earlier this year on a Motion for Summary Judgment under the Privette Doctrine and won judgment on behalf of the client/tenant. While that MSJ was pending, Plaintiff surreptitiously added the building’s owner to the suit with a DOE Amendment, after several months earlier learning the owner and then tenant were entities operated by the same individual. However, Plaintiff never informed counsel or any other party of the filing. Moreover, after the MSJ was granted, Plaintiff then waited several more months to serve the building’s owner.
Read the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Insurer Has Duty to Defend Faulty Workmanship Claim
January 22, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe magistrate judge recommended a determination that the insurer owed a defense to the subcontractor sued for faulty workmanship. Hanover Lloyds Ins Co. v. Donegal Mut. Ins. Co., 2023 U.S. Dist. LEXIS 180877 (W.D. Texas Oct. 5, 2023).
Poe Investments, Ltd. entered into an agreement with Jordan Foster Construction, LLC for construction of an auto sales and service facility ("Facility"). Jordan hired multiple subcontractors, including Texas Electrical Contractors, LLC ("TEC"). Subsequently, Poe sold the Facility to 6330 Montana, LLC ("Montana").
Montana filed suit against Jordan for breach of express warranties, breach of contract, and negligence. Jordon filed a third-party complaint against its subcontractors, including TEC. Jordan alleged that TEC provided "defective and negligent construction work" while carrying out the provision and installation of electrical and fire alarm systems at the Facility.
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Perez Broke Records … But Should He Have Settled Earlier?
February 19, 2024 —
Sofya Uvaydov & John F. Watkins - Kahana FeldIn 2021, Mark Perez’ Labor Law 240(1) lawsuit made legal news by breaking the record of the highest appellate-sustained pain and suffering award in New York history. While that record was short-lived, it still maintains its place as New York’s highest-ever pain and suffering award for a brain injury. This January 17th, the Appellate Division, First Department revisited the litigation but, this time, in a dispute between Perez and his then-lawyer, Ben Morelli and the Morelli Law Firm. Mr. Perez claims breach of contract over a 10% additional contingency fee charge related to the Perez v. Live Nation appeal and breach of fiduciary duty by his counsel in failing to convey settlement offers during the lifetime of the case. The Morelli firm counters, among other things, that the prior settlement offers – a $30 million offer during the 2019 trial and intermediate sums during the appellate stage – were still lower than the ultimate $55 million settlement. No harm, Mr. Morelli argues, and thus no foul in failing to convey the offers.
But is that so? Did Mark Perez ultimately receive more money in his $55 million settlement than from the $30 million settlement offer mid-trial? Despite the glaring $25 million difference, the surprising calculations show that Perez would have been financially better off taking the $30 million mid-trial settlement.
Reprinted courtesy of
Sofya Uvaydov, Kahana Feld and
John F. Watkins, Kahana Feld
Ms. Uvaydov may be contacted at suvaydov@kahanafeld.com
Mr. Watkins may be contacted at jwatkins@kahanafeld.com
Read the full story...
Court Grants Insurer's Motion for Summary Judgment After Insured Fails to Provide Evidence of Systemic Collapse
April 15, 2024 —
Tred R. Eyerly - Insurance Law HawaiiWith the insurer conceding that there was evidence of potential collapse at portions of eight specific building locations, the court granted the insurer's motion for partial summary judgment in determining no additional buildings suffered from collapse. Exec. 1801 LLC v. Eagle W. Ins. Co., 2024 U.S. Dist. LEZXIS 5923 (D. Or. Jan. 11, 2024).
Executive 1801 owned a group of six buildings with eighty-six residential units. The court previously granted partial summary judgment on Executive 1801's rain damage claim, leaving only claims regarding collapse. Eagle insured "the property for direct physical los or damage to Covered Property . . . caused by or resulting from any Covered Cause of loss." The policy further provided, "We will pay for direct physical loss or damage to Covered Property, caused by collapse of a building or any part of a building insured under this policy, if the collapse is caused by . . . hidden decay."
Read the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com